| 4 October 2009 | |
| Fridge (at left) completes kitchen equipment | New hall can now be used to show films or presentations |
| First event was Zebon Copse Fete on 5 September | |
![]() |
|
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
| Week ending 4 September 2009 | |
![]() |
![]() |
| Centre renamed to ZCC | Play area completed |
![]() |
![]() |
| Stage complete | Kitchen units complete |
![]() |
![]() |
| Front paths complete | Cycle rack installed |
| Week ending 28 August 2009 | |
![]() |
![]() |
| New play equipment installation completed and safety surface laid | |
![]() |
![]() |
| Back of stage curtains installed | |
![]() |
![]() |
| Acoustic partition refurbished | Lobby carpet laid |
![]() |
![]() |
| Water boiler installed in kitchen | Front path relaid without step |
| Week ending 21 August 2009 | |
![]() |
![]() |
| New play equipment being installed. Safety surface to follow. | |
![]() |
![]() |
| Kitchen units in place. Worktops to be completed. | |
![]() |
![]() |
| Base for cycle rack | Front path being prepared for relaying |
| Week ending 14 August 2009 | |
![]() |
![]() |
| Kirtchen units partly installed | |
![]() |
![]() |
| New toilets well advanced | |
![]() |
![]() |
| Store room shelving in place | |
![]() |
![]() |
| Cycle rack area cleared | Doors fitted to goalpost store |
| Week ending 7 August 2009 | |
![]() |
![]() |
| Kitchen units going in | Outside tap installed |
![]() |
![]() |
| Acoustic screen repaired | Glue spread on wall by vandals |
| Week ending 31 July 2009 | |
![]() |
![]() |
| Stage surface staining in progress | Carpet laid in Meeting Room |
![]() |
![]() |
| Kitchen units await installation | New toilet fittings being installed |
| Week ending 24 July 2009 | |
![]() |
![]() |
| Interiror painting continues | Stage decking under construction |
![]() |
![]() |
| Kitchen floor preparation for covering | |
| Week ending 17 July 2009 | |
![]() |
![]() |
| Play area fencing | Choice of colours for stage |
| Week ending 10 July 2009 | |
![]() |
![]() |
| Extension to play area | Lining the goalpost store |
![]() |
![]() |
| Steps up to the stage | |
![]() |
![]() |
| Facing the front of the stage | Contrast surrounds for switches |
| Week ending 3 July 2009 | |
![]() |
![]() |
| Suspended ceilings in both main halls | Recessed lights in new ceilings |
| Week ending 26 June 2009 | |
![]() |
|
| Halls readied for installation of lowered acoustic ceiling and re-painting | |
![]() |
![]() |
| Stage frame complete | Light well frame ready for lower ceiling |
![]() |
![]() |
| Kitchen cleared for re-decorating | New aluminium guttering and downpipes |
| Week ending 19 June 2009 | |
![]() |
![]() |
| Painting the under-stage goalpost store | Access to the under-stage goalpost store |
![]() |
![]() |
| Sanitaryware in the new toilet block | New ceiling lights in the Meeting Room |
| Week ending 12 June 2009 | |
![]() |
![]() |
| Stage End cladding complete | Stage frame takes shape |
![]() |
![]() |
| Office decorated | Kitchen sink plumbing |
| Week ending 5 June 2009 | |
![]() |
![]() |
| New lowered kitchen ceiling | Stage end plastering |
![]() |
![]() |
| New link door looking from sports area | Wood cladding to stage end store rooms |
| Week ending 29 May 2009 | |
![]() |
![]() |
| Stage area progress | Trial colours in hallway |
| Week ending 22 May 2009 | photos by Andrew Macallan |
![]() |
![]() |
| Stage end roof tiled | Stage end bricks completed |
![]() |
![]() |
| Store room plastered | Kitchen doors fitted |
| Week ending 15 May 2009 | |
![]() |
![]() |
| Tiling the quadrangle roof | Some of outside wood repainted |
![]() |
![]() |
| Stage end walls complete | Stage side door |
![]() |
![]() |
| Painting the meeting room walls | New openings into main hall |
| Week ending 1 May 2009 | |
![]() |
![]() |
| Old stage end interior wall partly removed | Office (L) new kitchen servery (R) |
| Week ending 24 April 2009 | |
![]() |
![]() |
| Roof covered over quadrangle | New toilets taking shape |
![]() |
![]() |
| Good progress at the stage end | |
| Week ending 17 April 2009 | |
![]() |
![]() |
| New roof windows in old hall | New store rooms at North end |
![]() |
![]() |
| Quadrangle roof trusses | North wall with opening for football goal storage |
| Week ending 3 April 2009 | |
![]() |
![]() |
| New acoustic barrier in roof space | New store room in quadrangle |
![]() |
![]() |
| Quadrangle end wall | Stage end wall |
![]() |
![]() |
| Preparing for quadrangle wall | New path with tarmac |
| Week ending 20 March 2009 | |
![]() |
![]() |
| New path to play area | Preparing for new fire door |
![]() |
![]() |
| Quadrangle infill concrete floor | Stage end concrete floor |
| Week ending 13 March 2009 | |
![]() |
![]() |
| Pouring concrete for the quadrangle infill floor | |
![]() |
![]() |
| Pouring concrete for the quadrangle infill floor | |
![]() |
![]() |
| Quadrangle footings | Stage and storage footings |
| Week ending 6 March 2009 | |
![]() |
![]() |
| Andrew Macallan, architect, and stage end footings | New walls in the old hall and kitchen |
![]() |
![]() |
| Kitchen end of old hall | New hall |
![]() |
![]() |
| Old hall quadrangle side | North end stripped ready for removal |
![]() |
![]() |
| Drains for new toilet block | |
![]() |
![]() |
| Footings for stage end | Old play equipment removed |
Before refurbishment started on 16 February 2009 |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
| Photos by David Jackson except where stated otherwise | |